Realistic ranges (India, experienced teams, 2026)

  • Brochure business website: 3–6 weeks including content and revisions
  • E-commerce store (moderate catalogue): 6–12 weeks
  • Focused web app MVP: 8–16 weeks for one primary user journey
  • Complex SaaS with payments, roles, admin: 4–9 months phased
  • Enterprise portal with integrations: often 6–12+ months in phases

What actually causes delays (often on the client side)

  • Content and photos not ready when development starts
  • Multiple decision-makers giving conflicting feedback
  • “Small” scope additions without timeline adjustment
  • Third-party API access or bank approvals for payments
  • Legal review of terms, privacy policy, or compliance copy

How executives speed projects up

Assign one decision-maker. Prepare content early. Accept phased launch—core features first, nice-to-haves in v1.1. Weekly 30-minute reviews beat monthly big-bang approvals. The best projects feel boring because communication is steady.

LogicLitzLogicLitz

FAQ

Questions, answered.

Straight answers about how we work, where we ship from, and what working with LogicLitz looks like.

Quotes assume timely feedback, frozen scope, and ready content. Reality adds change requests, holidays, integration delays, and learning what users actually need. Phased quotes with explicit assumptions reduce surprises.

Need a timeline you can take to your board?

Share your scope—we will map phases, dependencies, and a realistic launch window.